Webinar - Sky Central Case Update
Agenda
The High Court has handed down the hotly anticipated judgment in Sky & Mace v Riverstone, which concerned a claim by Sky and Mace for the cost of remedial works to the roof at Sky Central. We will be covering the key issues in dispute and the Court’s findings, which are likely to be of general interest to contractors and CAR practitioners (and enthusiasts!).
Speaker
Rob Goodship, Associate Partner
Cladding PI Notifications - A View from Down Under
A recent decision in the Federal Court of Australia provides guidance on broad professional indemnity insurance notifications for external cladding works, confirming that a wide problem may be validly notified with reference to appropriate supporting information - MS Amlin Corporate Member Ltd v LU Simon Builders Pty Ltd [2023] FCA 581.
A full copy of the judgment can be found here.
The Policies
LU Simon Builders Pty Ltd and LU Simon Builders (Management) Pty Ltd (the “Policyholders”) operated a construction and project management business. Professional indemnity (“PI”) insurance was arranged through local Australian and London placing brokers for the 2014/2015 period, including excess layers.
The insuring clause provided cover for civil liability arising from claims first made against the Policyholders during the policy period, and reliance was placed upon section 40(3) of the Insurance Contracts Act 1984, whereby an insurer is also liable for claims made after expiry of the period of insurance:
“where the insured gave notice in writing to the insurer of facts that might give rise to a claim against the insured as soon as was reasonably practicable after the insured became aware of those facts but before the insurance cover provided by the contract expired”.
This creates a statutory mechanism similar to the common position in the English PI market, where claims made covers are frequently extended to allow notification of circumstances known to the policyholder that may give rise to a claim: if notification of circumstances is made during the policy period then the third party claim itself – even though it may actually come in at a later date – is deemed to have been made during that same policy year.
The Claims
In 2019 proceedings were commenced against the Policyholders by developers and owners of Atlantis Towers in Melbourne, alleging that unsuitable ”Alcotex” aluminium composite panels (“ACP”) were used as cladding for the building (the “Atlantis Claims”). The Policyholders sought indemnity for the Atlantis Claims, and excess layer insurers applied for a declaration that the PI policies would not respond.
The Atlantis Claims came about following investigation by the Metropolitan Fire Brigade (the “Fire Brigade”) and Municipal Building Surveyor for the City of Melbourne (the “Municipal Surveyor”) into a fire on 25 November 2014 at Lacrosse Tower, another building constructed by the Policyholders. The investigation found that ACP at Lacrosse Tower (Alucobest) was not compliant with the Building Code of Australia, and had contributed to the rapid spread of fire.
The Victorian Building Authority (the “Building Authority”) subsequently commenced an investigation and audited around 170 high-rise buildings in Melbourne. The Building Authority concluded that ACP on the Atlantis Tower (Alcotex) was combustible, and Building Orders were issued requiring replacement.
The Notifications
The dispute centred around two notification emails headed “Potential Claim”, sent to insurers in May 2015, neither of which identified Atlantis Towers or the Alcotex brand of ACP which had been used in its construction.
The first notification email referred to: “a notification of circumstances that may result in a claim under [the Policyholders’] Policy … Really most of the noise is around the press release … No formal claim has been made against [the Policyholders] at this point in time”.
The email attached: (1) a newspaper article dated 28 April 2015, referring to the Building Authority’s investigation into the Policyholders’ building practices, to identify whether non-compliant ACP had been used elsewhere; and (2) a document headed “Lacrosse Apartments - Docklands” including commentary from the managing director of the Policyholders in relation to ACP having been widely used in Australia for decades with “no like product passing the test for combustibility”, and referencing a potential class action by owners of Lacrosse Tower.
The second notification email attached a report on Lacrosse Tower by the Fire Brigade entitled “Post Incident Analysis Report”, together with the design and construct contract. The report stated that the Fire Brigade was not aware of any competitor aluminium / polyethylene panel product which had satisfied combustibility tests, and expressed the Fire Brigade’s firm opinion that ACP without appropriate accreditation / certificates of conformity represented an unacceptable fire safety risk, given the need to prevent similar incidents. The Fire Brigade’s report contained hyperlinks to four media reports, suggesting that the Building Authority’s audit had revealed a pattern of poor compliance with regulations, and that “buildings may be a risk to occupants in a fire situation”.
The Decision
His Honour Justice Jackman concluded that the notification emails clearly pointed to a wider problem than one confined to the Lacrosse Tower, or to Alucobest products. The reference to broader investigations, alongside the proposal form statement that 100% of the Policyholders’ work in the last financial year related to high-rise buildings, had the effect of conveying to insurers that there was (at least) a real and tangible risk of the Policyholders facing claims for rectification of that aspect of its work on this building, and on others that it had constructed.
Applying principles discussed in P&S Kauter Investments Pty Ltd v Arch Underwriting at Lloyd’s Ltd [2021] NSWCA 136, the Court acknowledged notification need not be given in a single document, nor the likely claimant(s) identified. Information included by hyperlinks formed part of the notification, since the task of clicking “is not significantly more demanding than turning a physical page” - provided that the link is to a specific page or document. Opinions expressed by public authorities with appropriate expertise (such as the Fire Brigade or the Municipal Surveyor) were held to be capable of constituting “facts” for the purpose of s.40(3), despite the contrary Federal Court decision in Uniting Church (NSW) v Allianz Australia Ltd [2023] FCA 190.
Given a clear causal connection between investigations reported in the notification emails, and later proceedings against the Policyholders, the Court concluded that insurers had been notified before expiry of the policies of facts giving rise to the Atlantis Claims, within the meaning of s.40(3).
English Law
Australia is a common law jurisdiction originating from the English legal system, applying statutory provisions enacted by its various states and federal governments.
Policyholders are similarly able to make “hornets’ nest” notifications under English law, i.e. general notification of a problem even where the cause of the problem or its potential consequences are not yet known (HLB Kidsons v Lloyd’s Underwriters [2008]; Kajima UK Engineering v The Underwriter [2008]; Euro Pools plc v RSA [2019]).
The operation of notification of circumstances provisions under liability policies is often contentious, and careful consideration should be given to the content and timing of notices to insurers, with supporting documents, to maximise the scope of cover. Policyholders should be mindful of precise wording in their PI policy conditions on the knowledge threshold for notifications (whether based on “may” or “likely to” give rise to claims language), and ensure that the trigger remains consistent between policy years and insurance layers where possible, in order to avoid potential gaps in cover.
Amy Lacey is a Partner at Fenchurch Law
Reach for the Sky? – judgment handed down on Sky Central
Sky UK Limited & Mace Limited v Riverstone Managing Agency Limited & Others [2023] EWHC 1207 (Comm)
Summary
The High Court has handed down the hotly anticipated judgment in Sky & Mace v Riverstone, which concerned a claim by Sky and Mace for the cost of remedial works to the roof at Sky Central, Europe’s largest flat timber roof. The sums claimed for the two remedial schemes put before the Court were both in excess of £100m.
Whilst Sky, as principal insured and loss payee under the building contract, has been awarded an indemnity in principle, the quantum of that indemnity is subject to either agreement or, failing that, determination by the Court, given Mr Justice Pelling’s finding that none of the remedial schemes put before the Court sufficiently represented the remedial works necessary to address the damage as at the end of the Period of Insurance. That said, the Judge found that one of the schemes presented by insurers “most closely approximates” to the damage in need of remediation at the end of the Period of Insurance, and has encouraged the parties to agree the quantum of the appropriate temporary works which need to be added to that scheme.
Issues
The full judgment is worth a read for all CAR practitioners (and enthusiasts) but the real take aways are:
DE5
Whilst Sky is the first court decision anywhere in the world to consider the DE5 defect exclusion, it actually does no more than provide (at paragraph 29) a slightly clearer articulation as, based on the Judge’s findings, he didn’t need to consider what actually constituted an additional cost of any additional improvement works.
The reason for that is because his judgment was premised on one of insurers’ schemes being the most appropriate (in the circumstances) which (unsurprisingly) did not include any improvements to the original design, plan, specification, materials or workmanship.
Co-insurance
Sky follows closely after the Court of Appeal’s decision in RFU that was handed down in April (https://www.fenchurchlaw.co.uk/worth-a-try-judgment-handed-down-on-rugby-football-union-appeal/).
The Judge followed the reasoning in the first instance decision in RFU which Lord Justice Coulson said was “unassailable” by the Court of Appeal. Here, Mace was found to be a co-insured under the project policy but, as a result of the building contract entered into with Sky, only to Practical Completion (“PC”) and not to expiry of the Maintenance Liability Period (“MLP”) - only Sky had the benefit of that cover.
Mr Justice Pelling rejected Mace’s argument that a distinction should be drawn, and that it therefore benefited from, being a named in the policy (as opposed to falling into a prescribed category) as being “unprincipled and unsupported”. He found that there was “ample authority” that when deciding the scope and extent of the insurance cover available, it was necessary to consider the scope that the contracting insured agreed to procure, and that cover will not generally extend beyond what is contained in that agreement.
Mr Justice Pelling confirmed (at paragraph 58), and in line with the thinking of the majority in Gard Marine, that the effect of this particular contract was that neither Sky nor insurers can recover any pre-PC loss or damage against Mace, but that Mace was required to remediate and has no entitlement to a sum beyond that which was recovered under the policy.
Physical damage
The judge rejected insurers' definition of physical damage as occurring at a ‘tipping point’ when “structural change of such severity as to require replacement of the affected timber” as being "impermissibly narrow".
Instead he found that the physical damage occurred once water entered the roof cassettes on the basis that “the entry of moisture into the cassettes during the Period of Insurance is in my view a tangible physical change to the cassette as long as the presence of the water, if left unattended, would affect the structural stability, strength or functionality or useable life of the cassettes during the Period of Insurance or would do so if left unremedied”.
In relation to the timing of the occurrence of damage, this is arguably in line with Tioxide where it was found that damage occurred once the environmental conditions where damage was liable to occur were present.
The articulation in Sky is potentially wider than that though, which is likely to be very helpful for policyholders when there is ambiguity over the timing of the damage occurring, as it permits the earliest possible date on which damage is liable to occur if left unattended, which is frequently a source of dispute, particularly in relation to water ingress claims.
Aggregation/ deductibles
The other major battle ground between Sky/Mace and insurers, and a point that this is increasingly being taken by CAR insurers in relation to modern methods of construction (including cassettes and modular pods), was the applicable number of deductibles which was determined by the number of ‘events’.
Insurers’ position was that the damage to each of the 472 cassettes was an ‘event’, whereas the Claimants said that there was one event, namely the decision not to use a temporary waterproofing system when installing the roof cassettes, which permitted water ingress during construction.
Mr Justice Pelling said that, in this policy, the “single unifying event must be an error or omission in the design plan specification materials or workmanship of the property Insured that has suffered damage as a result of such defect” when a claim was recoverable under DE5.
Applying the unities of time, place and cause, and following Mr Justice Butcher's finding in Stonegate (https://www.fenchurchlaw.co.uk/court-hands-down-judgment-in-much-anticipated-covid-19-bi-cases-the-takeaways-for-policyholders/) that a decision (or plan) was capable of being an event if it satisfied those unities, the judge agreed with Sky and Mace that there was only one event and, therefore, one deductible was to be applied to Sky's claim.Appropriate remedial scheme
The claim presented by Sky and Mace was slightly unusual given that the remedial works had not taken place by the time the claim got to trial, which seemingly resulted in the Judge being in some difficulty when determining the appropriate indemnity. Helpfully for policyholders though, Mr Justice Pelling’s instinct in response to assertions that Sky and Mace’s claims had failed as neither of their schemes were ultimately awarded was that it would be “counter intuitive” that an insured which had proved some damage would be left without remedy.
The actual quantum of Sky’s claim remains unresolved, but the judge saw no difficulty in principle with the various schemes being ‘mixed and matched’ in order to identify the appropriate indemnity.
Comment
Although the judgment does not delve into the correct interpretation and application of DE5 as perhaps hoped, it does contain a number of helpful nuances in relation to typical coverage issues under CAR policies, which will be helpful to property and contract works policyholders generally.
Rob Goodship is an Associate Partner at Fenchurch Law
Webinar - Tackling Co-Insurance: Court of Appeal hands down judgment in Rugby Football Union
Agenda
Associate Partner, Rob Goodship will be delving into the tricky issues of co-insurance for contractors, including an analysis of the recent decision of the Court of Appeal and some tips for avoiding disputes.
Speaker
Rob Goodship, Associate Partner
Worth a Try? – judgment handed down on Rugby Football Union appeal
FM Conway Limited v The Rugby Football Union, Royal & Sun Alliance Insurance PLC, Clark Smith Partnership Limited
The Court of Appeal has handed down its judgment following FM Conway’s appeal of the High Court’s decision that it did not enjoy the same level of cover as its employer. Our previous article commenting on the first instance judgment can be found here.
Summary
The decision regards the potentially complicated factual and legal issues about the nature and extent of insurance cover obtained by one party on behalf of another. It was common ground at the first instance hearing that FM Conway was an insured under the project policy secured for the refurbishment of Twickenham stadium, but the extent of that cover was disputed by insurers.
FM Conway’s appeal was rejected by the Court of Appeal, with the leading judgment from Lord Justice Coulson providing a firm endorsement of Mr Justice Eyre’s decision that FM Conway was not insured under the project policy for damage to existing structures caused by its own defective work, but cover was instead restricted to specified perils in accordance with the (unamended) JCT Option C.
It is clear from the judgment that Lord Justice Coulson was in full agreement with Mr Justice Eyre, referring to his decision as “careful”, “unassailable” and “entirely in accordance with the authorities”.
Issues
The background facts are contained in our previous article but, in short, the underlying claim includes a subrogated claim by RSA in relation to the cost of remediating damaged cables, for which it had indemnified RFU as principal insured. FM Conway raised a co-insurance defence to that claim, asserting that it enjoyed the full benefit of the project policy obtained on its behalf by RFU.
FM Conway appealed the first instance decision on five grounds, albeit ground 1 was clearly FM Conway’s primary argument: whether the High Court applied the correct test for ascertaining the necessary authority and intention of the insuring party, the RFU. It was submitted on behalf of RFU and RSA, and then accepted by Lord Justice Coulson, that if ground 1 failed then so too must grounds 2, 3 and 4 as they were largely variations of the first ground and/ or were contingent on that ground succeeding.
It was held by the Court that Mr Justice Eyre did apply the correct test, given that he “paid particular attention to the underlying contract between the RFU and FM Conway. In that, he was following what Lord Toulson said was the correct approach in Gard Marine”. Lord Justice Coulson went on to say that “in any case where there is an underlying contract … it would be counter-intuitive if that was not at least the starting point for any consideration of authority and intention” to insure.
Lord Justice Coulson went on, as Mr Justice Eyre had in the first instance decision, to make clear that whilst the pre-contractual discussions between representatives for Conway and the RFU, respectively, regarding insurance arrangements could be taken into account (which were the main thrust of Conway’s argument that it had wider cover), they could not displace the clear interpretation of the building contract.
It was affirmed by the Court that “extraneous evidence” of a contrary authority or intention to insure could be relied on (similarly to Mr Justice Eyre’s finding that “compelling evidence” could be relied on), but the relevant investigations “will start (and possibly finish) with the underlying contractual arrangements agreed between the parties”.
The Court also made frequent reference, contrary to FM Conway’s reliance on the witness evidence which it said demonstrated an authority and intention of the RFU to secure wider cover, that both parties were represented by legal and insurance professionals such that had there been an intention to secure wider cover beyond that in Option C of the JCT Contract then it would have been reflected in the building contract ultimately agreed. Lord Justice Coulson said that to adopt FM Conway’s attempt to rely on early/ pre-contract discussions was “untenable” as it would enable a party to “ignore any subsequent stages of the actual negotiations”.
Guidance on co-insurance generally
Following his summary of the law in this area generally, Lord Justice Coulson provided (at paragraph 53 of the judgment) the following guidance in relation to co-insurance:
“53.1 The mere fact that A and B are insured under the same policy does not, by itself, mean that A and B are covered for the same loss or cannot make claims against one another;
53.2 In circumstances where it is alleged that A has procured insurance for B, it will usually be necessary to consider issues such as authority, intention (and the related issue of scope of cover). Such issues are conventionally considered by reference to the law relating to principal and agent …
53.3 An underlying contract between A and B is not a necessary pre-requisite for a proper investigation into authority, intention and scope …
53.4 On the other hand, where there is an underlying contract then, in most cases, it will be much the best place to find evidence of authority, intention and scope …
53.5 That is not to say that the underlying contract will always provide the complete answer. Circumstances may dictate that the court looks in other places for evidence of authority, intention and scope of cover”
Comment
Whilst the result is not surprising (especially as Lord Justice Coulson said that the first instance decision was in accordance with the existing authorities), it represents a clear articulation of the principles in this often complex area.
For policyholders in FM Conway’s shoes, it is key that if there is an intention for contractors to enjoy the same level of cover under the project policy as the employer/ principal insured, that the contractual documents make that clear and, where necessary, any standard forms are appropriately amended. That way, there is no need to look for other compelling or extraneous evidence to demonstrate that wider authority and intention which, as is made clear in the facts of this case, might be difficult to do.
Rob Goodship is an Associate Partner at Fenchurch Law
Building a safer future: the courts’ approach to fire safety cases
The Grenfell tragedy in 2017 has prompted safety investigations in myriad buildings across the UK, with owners and occupiers questioning whether other settings are similarly defective. Many disputes have arisen, with a handful of cases now determined following trials in the Technology & Construction Court. Overall the courts have adopted a robust approach to responsibility for cladding defects, rejecting typical defence arguments around scope of duty, causation and assessment of loss.
Recent Judgments
Martlet Homes Ltd v Mulalley & Co. Ltd
In July 2022, the claimant was awarded £8 million in damages to remediate high rise residential blocks in Gosport where a “StoTherm Classic” cladding system, including combustible expanded polystyrene insulation, had been applied to external walls during refurbishment in 2005 - 2008. This was held to contravene fire safety standards (the specification breach case), and the system had been defectively installed with inadequate fire breaks (the installation breach case). Costs incurred in removal and replacement of the cladding with a non-combustible alternative could be recovered, together with expenses of a waking watch fire patrol interim measure.
St James’s Oncology SPC Ltd v Lendlease Construction (Europe) Ltd & another
In October 2022, a company set up by Leeds Teaching Hospitals NHS Trust to deliver a new oncology centre was successful in its £5 million claim against Lendlease, based on fire safety and electrical engineering defects to an internal plant room. The defendants’ argument that derogation from applicable standards had been approved by all parties in a revised fire strategy document was rejected, given the overriding contract obligations: “Lendlease was at all times responsible for the design of the Works and for achieving compliance with the requirements of the D&B Contract, irrespective of any review, approval or comments made by Project Co and/or the Trust. This seems … to render the question of approval otiose”.
LDC (Portfolio One) Ltd v George Downing Construction Ltd & European Sheeting Ltd
In December 2022, the owner of student accommodation blocks in Manchester secured judgment in excess of £21 million for remedial works and lost rental income, against a specialist sub-contractor responsible for inadequate fire stopping/barriers, and composite cladding defects which led to substantial water ingress. The claimant and first defendant agreed to settle the claims between them for c. £17 million shortly before trial; the second defendant was insolvent and unrepresented at the hearing, which proceeded in any event as the liquidator could not consent to judgment being entered.
Performance Standards
The defendant contractors were in each case appointed pursuant to JCT Design and Build Contracts, with terms including an unqualified design and specification duty, obligation to comply with statutory requirements, and duty to exercise reasonable skill and care.
The judgments include discussion on performance standards and reaffirm the MT Hojgaard [2017] UKSC 59 principle, that - if there are two clauses imposing different or inconsistent design requirements, the courts are likely to interpret the less demanding clause as a minimum obligation, since treating it as qualifying the other clause gives a meaning which effectively renders the more demanding provision redundant.
The St James’s Oncology and LDC (Portfolio One) cases illustrate how bespoke amendments to standard form contracts may be used to improve prospects for recovery down the contractual chain, through “back to back” requirements for sub-contractors to indemnify the employer against liability arising under the main contract as a result of sub-contract breaches, and acknowledging that associated losses are within the parties' contemplation.
Building Regulations
The analysis of statutory requirements is particularly illuminating, in view of ubiquitous disputes over interpretation of relevant provisions now acknowledged by the government to have been “faulty and ambiguous”.
In Martlet v Mulalley, the judge concluded that Approved Document B (“ADB”), Fire Safety, 2000 edition (with 2002 amendments) does not mean that whatever was not expressly prohibited was permitted and acceptable; and ADB, 2006 edition, marked a significant change in guidance from the earlier regime, with only materials of limited combustibility to be used as external wall insulation in buildings over 18 metres.
Further, the Building Regulations 2000, Schedule 1, B(4)1 requirement for external walls to “adequately” resist the spread of fire, having regard to a building’s height, use and position, turned on whether the contractor had followed guidance in BRE 135 (2003), which recommended that combustible cladding should not be used on high rise residential blocks unless it met the Annex A performance standard in accordance with the test method set by British Standard 8414-1. It was not sufficient to “blindly” rely on a British Board of Agrement (BBA) certificate for the cladding system.
Negligence
The selection and use of a cladding system with combustible EPS insulation in Martlet v Mulalley was in breach of the contractor’s obligation to exercise the degree of skill and care in its design of the work as would an architect or other professional designer.
In reaching this decision, the judge rejected defence arguments to the effect that they cannot have been negligent because everyone else was making the same mistakes. On a proper application of the Bolam principle, there must be “evidence of a responsible body of opinion that has identified and considered the relevant risks or events and which can demonstrate a logical and rational basis for the course of conduct or advice that is under scrutiny”. A defendant is not exonerated simply by proving that others were equally negligent (199 Knightsbridge Development Ltd v WSP UK Ltd [2014]).
Negligent design in relation to cladding works means that professional indemnity policies are likely to be triggered, and exclusions for contractual liabilities won’t usually apply.
Failure to comply with building regulations may be strong evidence of breach of a designer’s duty to exercise reasonable skill and care, in the absence of an express clause requiring adherence to statutory requirements, as discussed in LDC (Portfolio One).
Causation
Another defence commonly raised in cladding disputes is that enhanced fire safety standards implemented after completion of the contract works, and/or the changed regulatory perspective post-Grenfell, are the true cause of remedial action undertaken or proposed. This was rejected in Martlet v Mulalley, with the judge suggesting that an “effective cause” test would be more appropriate to a “but for” standard in this case, to avoid the claimant being left without a remedy.
Had the building owner succeeded only on the installation breach, it could have recovered the cost of repairing defects but not those of replacing the cladding. Both the installation and specification breach cases were upheld on the facts, so the owner was entitled to recover replacement costs.
Remedial Costs
In St James’s Oncology, the defendants’ argument that there was no intention to carry out remedial works was dismissed. The court is not normally concerned with how the claimant will use any damages awarded, providing the loss can be established, although intention may be relevant to the reasonableness of reinstatement and thereby the extent of loss. It was legitimate (and prudent) for the claimant to take account of commercial considerations and await conclusion of the proceedings before commencing planned remediation, given the defendants’ complete denial of liability until shortly before trial.
Remedial works to the Gosport towers were already complete when Martlet v Mulalley reached trial. Costs incurred are the starting point for what is reasonable in such cases, especially if works are carried out based on expert advice. The claimant has a duty to mitigate loss, “but the court will not be too critical of choices made as a matter of urgency or on incomplete information”. It is not sufficient that defects could have been rectified more cheaply; the defendant must prove the remedial scheme was unreasonable.
Further, the costs of temporary measures such as waking watch patrols are likely to be recoverable. The judge in Martlet v Mulalley dismissed the suggestion that this aspect of the claim was too remote, saying that any lack of awareness of the potential need for such interim protections in the context of combustible cladding was more reflective of a “culture of endemic complacency” than any reasoned assessment.
Where works of repair or reinstatement result in the claimant having a better or newer building than it would otherwise have had, a deduction for "betterment" will not usually be made if the claimant has no reasonable choice (Harbutt’s Plasticine v Wayne Tank [1970]). This includes betterment resulting from compliance with legislation introduced since the original works were carried out, imposing additional or enhanced standards.
Looking Ahead
The emerging direction of travel underlines the difficulty for designers (and insurers) in defending these types of claims.
The Building Safety Act 2022 provides further impetus on cladding disputes, introducing new causes of action for defective works and construction products, subject to a maximum 30 years’ retrospective limitation period. The Grenfell Inquiry phase 2 report is due for publication later this year, with Sir Martin Moore Bick’s findings expected to significantly impact upon the liability landscape, and potential manufacturer claims in particular.
Owners will look to progress claims swiftly in light of insolvency risks, with expert technical and quantum evidence crucial in justifying schemes of remedial work. Construction professionals with cladding exposures will be keen to extricate themselves through commercial settlements, whilst pursuing possible recoveries. Moving forward, contractors should endeavour to agree supply chains on back to back terms with their main contract, to limit exposures and improve prospects in the event of breach.
The courts’ focus on ensuring that buildings are made safe and compliant with current statutory requirements is closely aligned with public policy. Further developments in this area, including jurisprudence around Building Liability Orders and s.38 of the Building Act 1984, for example, are eagerly anticipated.
Authors:
Amy Lacey is a Partner at Fenchurch Law
Grace Williams is an Associate at Fenchurch Law
(New Home) Buyer Beware
Recent case law highlights the importance of adequate insurance cover for buyers of new homes, to remediate any latent defects identified post-completion, whilst the Building Safety Act 2022 implements significant changes to the new build warranty landscape.
In Griffiths and another v Gilbert [2022] EWHC 3122 (TCC) (6 December 2022), HHJ Sarah Watson (Principal Judge of the Technology and Construction Court in Birmingham) dismissed allegations that a director of the building contractor responsible for construction of the claimants’ property had fraudulently misrepresented that £2 million worth of NHBC cover would be obtained, covering the full build cost, rather than the standard £1 million limit for defects claims under the NHBC Buildmark policy.
After practical completion, a dispute arose concerning building defects and contamination of surrounding land. The claimants referred matters to the NHBC's dispute resolution service but subsequently withdrew from the process, unhappy with the initial response. Court proceedings alleging personal liability for fraudulent misrepresentation were commenced in 2014 and then stayed, pending the outcome of an arbitration pursued by the claimants against the contractor. In 2018 the arbitrator awarded substantial damages and costs to the claimants, which the contractor was unable to meet, and it went into insolvent liquidation. The claimants successfully recovered £1 million under the NHBC warranty, and court proceedings against the director were revived seeking recovery of outstanding losses.
The Judge held that elements of the tort of deceit were not made out in this case and the fraudulent misrepresentation claim failed. The director had confirmed the property would be built to NHBC standards and a Buildmark warranty would be obtained, but premium figures in the contract costings were estimates not representations. It was inherently unlikely the contractor would fraudulently represent the situation to save a small fee on a £2 million contract, knowing this would come to light when the NHBC certificate was provided. Further, NHBC was advised of the sale price at the outset with no question of “underinsurance”, analogous to standard property policies, where claims might be reduced if a building was insured for less than full reinstatement costs.
The judgment illustrates the limitations of new home warranties and how parties can extend the scope of cover for a price. In 2011, NHBC had offered to increase the cover to £2 million for an additional fee of approximately £4,500 but that proposal was not accepted by the claimants.
The importance of sufficient protection for buyers of new homes is also reflected in legislative changes under section 144 of the Building Safety Act. These provisions impose legal requirements on developers to provide new build warranties with a term of at least 15 years (increased from the usual 10 years period applicable previously), in line with the new prospective limitation period for claims under the Defective Premises Act 1972. Regulations are anticipated in 2023 imposing additional requirements on the kinds of defects covered, minimum policy limits, period during which the developer remains responsible, and financial penalties for non-compliance, following further industry consultation. Mandatory parameters of coverage should increase transparency for all concerned, helping to minimise the prospect of disputes.
Amy Lacey is a Partner at Fenchurch Law
Webinar - Differing Perspectives on the Building Safety Act 2022
Agenda
This webinar by Fenchurch Law’s Construction and Property Risks Group will be introduced by Joanna Grant, who leads the group and will feature sessions from Alex Rosenfield, Amy Lacey and Rob Goodship as follows:
Alex will address the new limitation periods for claims under the Defective Premises Act (which will either be 15 or 30 years, depending on when the claim accrued), as well as the new avenues of redress for claimants against (i) manufacturers or suppliers of construction products; and (ii) associated companies of subsidiaries or SPVs who undertook the original building work. The common objective of all of these claims is to ensure that, insofar as possible, leaseholders are not required to foot the bill for the significant costs of remediating defective buildings.
Amy will discuss the impact of the BSA for developers and managers of buildings with historical safety defects, including the “waterfall” approach to remediation costs implemented through industry levies, the Building Safety Fund and restrictions on service charge contributions for qualifying leaseholders.
Rob will round off with a discussion about the potential insurance implications for policyholders operating in the construction sector, focussing on those with emerging liabilities for historic works as a result of the retrospective change to the limitation period under the Defective Premises Act. This will include reference to difficulties policyholders may face under PI and PL policies, and how those difficulties might be managed.
Speakers
Alex Rosenfield, Senior Associate
Rob Goodship, Associate Partner,
Webinar - Damage: A Deep Dive
Agenda
This session will dig deeper into a subject touched upon briefly in David’s recent Defects Exclusions webinar. It will aim to provide a pathway through the leading authorities in relation to the various common types of damage encountered in construction projects, including physical rearrangement, overlaying of insured property with benign substances, and contamination. It will also look at the difference between development and discoverability in a damage context, and will consider the New Zealand case that arguably represents the higher water mark of damage authorities: Technology Holdings v IAG.
Speaker
Co-Insurance, it’s a bit of a scrum
The Rugby Football Union v Clark Smith Partnership Limited & FM Conway Limited [2022] EWHC 956 (TCC)
This recent High Court decision once again shines a light on the tricky issue of co-insurance under project CAR policies, in particular the difficulties faced by contractors of all levels when trying to demonstrate the extent of cover in the face of a subrogated claim from project insurers.
It’s the most noteworthy judgment on the issues since Haberdashers’ Aske’s Federation Trust in 2018 (which, as we’ve stated previously, is a bad decision for policyholders), and is a helpful refresh of the issues, if only to remind parties to construction projects to ensure that the contractual arrangements for any project accurately reflect the intention and authority of the party obtaining insurance cover for others.
Background
The Rugby Football Union (“RFU”) was undertaking significant works at Twickenham in 2012 in order to prepare for the 2015 Rugby World Cup. It engaged Clark Smith Partnership Limited (“Clark Smith”) to design buried ductwork which was to contain power cables, and FM Conway Limited (“Conway”) to install it. RFU and Conway contracted on the basis of a JCT Standard Building Contract without Quantities 2011 (“the JCT”), some of which (but importantly not all) was the subject of agreed amendments.
RFU asserted that the ductwork was defective which caused damage to the cables as they were pulled through (by a third party), which resulted in replacement costs of £3,334,405.26, for which it was indemnified by the project insurers, Royal & Sun Alliance Plc (“RSA”).
The project policy contained a DE3 standard form defects exclusion, which meant that the cost of addressing the defective ductwork was excluded, but the remedial cost of the consequential damage to the cables was covered.
RSA sought to recover those sums from Conway (and Clark Smith) in a subrogated recovery action on the basis that the damage had been caused by its defective workmanship. In response, Conway issued Part 8 proceedings seeking a declaration that it was a co-insured under the project policy and that it had the benefit of cover to the same extent as RFU (as principal insured), which prevented RSA from bringing the subrogated claim against it.
Issues
In relation to the claim brought by RSA (in relation to which it stood in RFU’s shoes), Mr Justice Eyre was asked to consider whether the sums paid by RSA to RFU were irrecoverable because RSA could not exercise subrogation rights and/ or on a proper analysis of the project policy and/ or the contract documents that RFU and/ or RSA were not entitled to claim the insured losses.
The judgment contains a very useful summary of the law regarding co-insurance to date, including the basis on which subrogated claims between parties to an insurance policy can be barred by reason of circuity of action (Co-operative Retail Services Ltd [2002] UKHL 17) and the basis on which one insured may obtain cover for another (Gard Marine & Energy Ltd [2017] UKSC 35). However, the key aspect here was not the existence of cover in the first place, but the extent of that cover for a co-insured.
The specific consideration here was whether Conway had the benefit of the full cover under the project policy, which provided cover for damage to other property insured caused by Conway’s defective works, or whether its cover was restricted to damage caused by Specified Perils as provided for by the unamended part of the JCT.
Mr Justice Eyre was at pains to stress (guided by the above authorities, but also National Oilwell (UK) Ltd [1993] 2 Lloyd’s Rep 582) that the contract is key when determining the intention and authority of the principal insured when securing cover, stating:
“74. What is important is that the authorities are clear that in order to determine whether the insurance cover which a policy effected by, in my example, the employer or contractor applies to the contractor or sub-contractor and if to what extent (with the latter point determining the extent to which they are co-insured) it is necessary to look to the terms of the contract between those parties. It is those terms which provide the key to the existence and extent of the insurance cover.”
“88. … when a person becomes a party as a consequence of the actions of another person then the terms of the contract between the insured party and that other govern the extent of the insurance”
In relation to the intention and authority of RFU, Mr Justice Eyre found (despite witness evidence to the contrary relied on by Conway, that the insurance obtained by RFU was intended to be more extensive than envisaged by the JCT), that the contract documents read together (including the JCT) did not demonstrate an intention for the project policy to create a fund which would be the sole remedy for loss suffered by RFU as a consequence of a breach by Conway.
Whilst Conway was an insured under the project policy, the extent of that cover was that as envisaged in the JCT and no wider, such that it was not a co-insured in relation to the damage for which RSA had indemnified RFU. He went on to find (again consistent with National Oilwell) that the waiver of subrogation clause in the policy only related to the matters for which Conway had cover under the policy, and so didn’t prevent a claim by RSA.
Comment
This judgment doesn’t alter the previous state of the law in this area, but is a salutary reminder to make sure that the contractual documents are in line with the expectations of the parties.
Mr Justice Eyre indicated that “compelling evidence to counter the inferences from the natural reading” of the JCT may have altered the result (which is in line with the “other admissible material” referred to in National Oilwell), but that evidence was not present here. Rather, the judge found it “surprising” that the JCT was subject to amendment elsewhere, but not in relation to the insurance for the works. If the parties had intended the extent of cover to be different from that envisaged by the unamended JCT, then presumably it would have been simple enough to reflect that in an amended version of the JCT. The absence of those amendments seems to have been an important consideration in relation to the parties’ intentions.
If there’s an intention for members of the project team to have a benefit under any project policy, it is vital that the underlying contractual documents accurately reflect the full extent of the principal insured’s intention and authority in that regard.
Rob Goodship is a Senior Associate at Fenchurch Law