Collisions, Allisions and Prudent Uninsureds - Technip v Medgulf, and insurance for unauthorised settlements

Technip Saudi Arabia Ltd v Mediterranean and Gulf Cooperative Insurance and Reinsurance Company [2023] EWHC 1859 (Comm) (21 July 2023)

This decision provides helpful insight into how the Courts will deal with insurance claims for sums due under a settlement agreement.

Technip was the principal contractor for a project in an offshore oil and gas field in the Persian Gulf. In 2015, a vessel that Technip had chartered collided with and damaged a platform in the field. Technip and the platform owner, KJO, reached a settlement for US$25 million, which Technip sought to claim from the defendant insurer (“Medgulf”), along with other alleged losses, under the liability section of its Offshore Constructions All Risks policy. The settlement had occurred some three years after Medgulf had declined indemnity for the original claim, instead telling Technip that it should act as a “prudent uninsured”.

Claiming losses under Settlement Agreements

Technip -v- Medgulf confirmed the general principle under English Law that it is not enough for a policyholder simply to prove that a settlement agreement reached with a third party is reasonable in order to claim for the resulting loss under a liability policy, but it must also prove that there was a legal liability to the third party and that the settlement does not exceed the amount of that liability. In other words, the law does not provide a carte blanche to policyholders to settle disputes with third parties and expect a liability insurer to pick up the tab.

Settlement Agreements and Insurer’s Consent

Liability policies very commonly require the insurer's consent before a policyholder takes various steps during a dispute with a third party. These can include admission of liability, settlement discussions, negotiations and entering settlement agreements.

Here, the Policy provided an indemnity to Technip for its 'Ultimate Net Loss' ("UNL"), which was defined as:

"the total sum the Insured is obligated to pay as Damages …"

Damages were defined as:

"…compensatory damages, monetary judgments, awards, and/or compromise settlements entered with Underwriters' consent, but shall not include fines or penalties, punitive damages, exemplary damages, equitable relief, injunctive relief or any additional damages resulting from the multiplication of compensatory damages". (Our emphasis)

Technip did not obtain Medgulf’s consent before concluding the settlement agreement, and Medgulf predictably argued that the settlement sum therefore did not fall within the definition of  “Damages”.

Technip successfully argued that the sums payable under the Settlement Agreement comprised, in part, "compensatory damages" and so fell under the definition of "Damages" under the Policy. Medgulf had argued that the four categories identified in the first part of the definition of “Damages” had a degree of separation and that, crucially, “compensatory damages” must be sums awarded by a court or tribunal, which would not be applicable to the US$25 million Technip paid to KJO. The Court rejected this argument, however, and did not view the four categories as disjunctive: the settlement payment was caught by the definition of “compensatory damages” within the ordinary meaning of the term, with the result that the absence of consent by Medgulf was irrelevant.

Furthermore, Technip argued that, even if the settlement sum did not constitute “compensatory damages” and instead was only potentially covered as a “compromise settlement”, there was still no need for Medgulf's consent given that it had refused to indemnify Technip in 2016 (three years before the Settlement Agreement) and told Technip to act as a 'prudent uninsured'. Technip contended that, in these circumstances, the provision requiring consent could not apply, as the provision presupposed the insurer's acceptance of liability under the Policy.

The Court agreed with Technip and held that it "would have little difficulty in concluding that the insurer had waived any requirement for the insured to seek its consent or was estopped from asserting that such consent should have been sought and insured". So, in short, the Court found that Medgulf was prevented from relying on the “Underwriter’s consent” part of “compromise settlements”.

Summary

Although Technip’s claim for an indemnity ultimately failed on other grounds, the Court’s comments concerning insurers' inability to rely on terms requiring their consent once they have told the policyholder to act as a prudent uninsured (or use similar language) are plainly useful for other policyholders. The decision stands in welcome contrast to the Privy Council’s judgment in Diab v Regent [2006] UKPC 29, which had seemingly held that, where an insurer has declined indemnity, a policyholder is still bound by all the claim conditions, including the need to seek insurer’s consent for a settlement. The policyholder in Diab had also raised an estoppel argument, which failed because the Court viewed the alleged representation of the insurer as essentially a warning not to pursue a claim under the policy, and not as an indication that, if the policyholder did pursue the claim, it would not be expected to comply with the procedural requirements of the policy.

Fun Fact: The event leading to the Damage in Technip -v- Medgulf was referred to throughout the Trial as an allision rather than a collision, an allision being where one of the objects involved is stationary.

Authors:

Dru Corfield, Associate

Toby Nabarro, Associate

Jonathan Corman, Partner


Challenging times for Zurich: insurer ordered to pay out on Covid 19 claim

World Challenge Expeditions Limited v Zurich Insurance Company Limited [2023] EWHC 1696 (Comm)

The court has held that, having operated a business travel policy in a certain way for nearly four years, Zurich was estopped from denying that it provided cover on that basis.

An estoppel by convention had arisen such that it would be inequitable for Zurich to resile from the common assumption between the parties as to the operation of the policy.

As such, the successful policyholder, World Challenge (represented by Fenchurch Law), was entitled to an indemnity of almost £9m, being the amount of refunds paid to its customers following the cancellation of its global programme of expeditions necessitated by the pandemic.

The court further criticised Zurich for its handling of the claim and the time that it taken to clarify its position.  This was a matter of utmost importance and urgency in circumstances where it was critical to World Challenge’s business and customer relations that it was able to confirm whether it had a covered claim.  Mrs Justice Dias commented that: “This is not an impressive performance even in the difficult circumstances of early 2020 and ordinary policyholders might well be appalled to think that a reputable insurance company could treat a long-standing and supposedly valued customer in this way”.

A full copy of the judgment can be found here.

Background

The policyholder, World Challenge, provides adventurous, “challenging” expeditions worldwide for secondary school students, or “challengers”.  As a result of the pandemic it was obliged to cancel nearly all of its booked expeditions for 2020.

The insurer, Zurich, provided World Challenge with wide ranging cover including cover for cancellation of trips by the challengers.

Prior to the pandemic, Zurich had handled and approved more than one hundred cancellation claims since 2016 in the amount of the refund paid to challengers. The amount of the refund, less an administration fee, was recorded against the aggregate deductible in the event of a trip cancellation. Prior to the onset of Covid-19, that aggregate deductible was never exhausted.

When the pandemic struck in early 2020, Zurich faced substantial claims for refunds to challengers for trips that would be cancelled in the coming months, and which would significantly exceed the aggregate deductible. World Challenge’s position was that Covid-19, and the mass trip cancellations which could eventuate, was precisely the type of ‘black swan’ event that it thought it had insurance cover for.  It sought confirmation of that cover from Zurich prior to cancelling the relevant trips and exposing itself to the millions of pounds of refunds to its customers that it would need to make as a result.

In light of the significant losses it now faced, Zurich, after an extended period of delays in confirming its position, in a complete volte-face sought to depart from the “common assumption” of cover for refunds and instead informed World Challenge that it only had cover (and only ever had cover) for irrecoverable third party costs (for example, hotel or airline costs which World Challenge had paid out and was unable to recover).

The claim

The issue before the court was the correct construction of the policy and whether Zurich was precluded by estoppel or collateral contract from denying that the policy provided the cover that World Challenge thought it had.

Mrs Justice Dias concluded that, although the policy in fact only covered irrecoverable third party costs,  Zurich’s previous conduct in agreeing claims in the amount of the refunds and setting them against the deductible had clearly conveyed to World Challenge that they shared its assumption as to the scope of cover and World Challenge was strengthened and confirmed in its own reliance on that assumption.

Zurich’s argument that the subjective understanding of its claims handlers was insufficient to establish any assumption on the part of the company was rejected.

Further, the court found that the delays in cancelling trips caused by Zurich’s delay in confirming its position on cover caused World Challenge to lose its opportunity to explore other avenues in order to maintain customer goodwill and manage its exposure.

It was therefore inequitable for Zurich to resile from the common assumption. Zurich had every opportunity to correct the error in handling claims, but took no steps to do so until such time as it became apparent that the aggregate deductible would be exceeded.

Conclusion

This judgment provides a welcome reminder to insurers about the importance of handling claims in a timely manner that responds to the needs of its customers, particularly in the face of a devastating loss with significant repercussions for the continued operation of its business.

Also welcome is the confirmation that the conduct of claims handlers in approving or rejecting claims will bind an insurer as they are the people charged with handling the claims on the company’s behalf.

From a legal perspective, in addition to being essential reading for anyone interested in the requirements of a variety of types of estoppel, practitioners will do well to take note of the comments made about the witness evidence and the dangers of putting forward statements that are inconsistent with the contemporaneous documents.  This made for an uncomfortable time for Zurich’s witnesses in the box, and should be a salutary tale, particularly given the spotlight on witness evidence in light of the recent changes to the rules in respect of trial witness statements.

Authors:

Joanna Grant, Partner

Rob Goodship, Associate Partner

Anthony McGeough, Senior Associate 


Not so peachy – a disappointing Covid-19 decision for policyholders

Bellini (N/E) Ltd trading as Bellini v Brit UW Limited [2023] EWHC 1545 (Comm)

In a month where Covid-19 decisions are coming in thick and fast, policyholders will be disappointed by the most recent judgment concerning a disease wording. A copy of the judgment can be found here.

On this occasion the policyholder, Bellini (N/E) Ltd, was issued with a policy by its insurer, Brit UW Limited, that contained an extension to business interruption cover for business interruption caused by damage arising from a notifiable disease manifested by any person whilst in the premises or within a 25-mile radius.

Disease wordings like these will be familiar to those who are acquainted with the FCA test case and Covid-19 litigation, but in this particular case the quirk is a reference to the defined term “damage” in the introductory paragraph to the extension. Damage within this policy was defined as “physical loss, physical damage, physical destruction”. However, it was common ground between the parties that there had been no physical loss of or damage to the policyholder’s premises or property.

The policyholder argued that policy provided both basic cover for physical damage and also extensions of cover for other matters that would not ordinarily result from or in physical damage. In particular, the provision of a radius clause of 25 miles for the manifestation of disease went beyond the basics of physical damage to the premises or property therein, which the policyholder asserted was reinforced by the court’s analysis of similar wordings in the FCA test case.

Among other arguments on the construction of the policy, the policyholder contended that if the extension only responded to physical damage it would “render any cover it provided illusory, and negate the purpose of the clause in providing cover for a notifiable disease that could manifest itself miles away”.

The court, however, was unpersuaded by the policyholder’s arguments, instead relying upon the “ordinary meaning” of the clause, which provided no cover in the absence of physical loss, damage or destruction. In particular, the court considered it to be significant that the clauses dealt with in the FCA test case were not expressed as to cover interruption caused by damage, and had been recognised as non-damage in that cover was not contingent on physical damage.

The court considered that the policyholder’s arguments effectively required it to re-write the policy contrary to the parties' express agreement and the established approach to contractual construction.

Comment

Recognising that the impact of a notifiable disease will be non-damage related losses, many wordings make it clear that the extension is intended to be triggered in the absence of physical damage, and that is how the clause would be understood to operate.

In circumstances where the parties agreed that a disease at the premises or within 25 miles of the premises does not cause physical damage, it is difficult to see what purpose, if any, can served by a clause that only provides cover for physical damage.

It is therefore difficult to reconcile the court’s attempts to give effect to the wording of the policy with what most policyholders (and we assume those insuring them) would expect to be covered when offering a 25-mile radius clause as part of the policy cover.

It is notable that the courts in the FCA test case grappled with similar difficulties on wordings where the standard form of certain clauses assumed the paradigm case of business interruption by reference to physical damage. The Supreme Court, albeit in the context of trends clauses, came to the view at [257] that the “reference to “damage” is inapposite to business interruption cover which does not depend on physical damage to insured property such as the cover with which these appeals are concerned. It reflects the fact that the historical evolution of business interruption cover was as an extension to property damage insurance. It was held by the court below, and is now common ground, that for the purposes of the business interruption cover which is the subject of these appeals, the term “damage” should be read as referring to the insured peril”. It appears that in the right circumstances the courts are not opposed to manipulating the wording of a policy to give it proper effect, and one might have expected the court in this matter to have taken a similar approach to the 25-mile radius clause.

Undoubtedly the market will be watching this one closely for any signs of an appeal, especially in light of the body of Covid-19 case law that appears to support a disease clause such as the one in dispute here.

Authors:

Anthony McGeough, Senior Associate

Joanna Grant, Partner


Building a safer future: the courts’ approach to fire safety cases

The Grenfell tragedy in 2017 has prompted safety investigations in myriad buildings across the UK, with owners and occupiers questioning whether other settings are similarly defective.  Many disputes have arisen, with a handful of cases now determined following trials in the Technology & Construction Court.  Overall the courts have adopted a robust approach to responsibility for cladding defects, rejecting typical defence arguments around scope of duty, causation and assessment of loss.

Recent Judgments

Martlet Homes Ltd v Mulalley & Co. Ltd

In July 2022, the claimant was awarded £8 million in damages to remediate high rise residential blocks in Gosport where a “StoTherm Classic” cladding system, including combustible expanded polystyrene insulation, had been applied to external walls during refurbishment in 2005 - 2008.  This was held to contravene fire safety standards (the specification breach case), and the system had been defectively installed with inadequate fire breaks (the installation breach case).  Costs incurred in removal and replacement of the cladding with a non-combustible alternative could be recovered, together with expenses of a waking watch fire patrol interim measure.

St James’s Oncology SPC Ltd v Lendlease Construction (Europe) Ltd & another

In October 2022, a company set up by Leeds Teaching Hospitals NHS Trust to deliver a new oncology centre was successful in its £5 million claim against Lendlease, based on fire safety and electrical engineering defects to an internal plant room.  The defendants’ argument that derogation from applicable standards had been approved by all parties in a revised fire strategy document was rejected, given the overriding contract obligations: “Lendlease was at all times responsible for the design of the Works and for achieving compliance with the requirements of the D&B Contract, irrespective of any review, approval or comments made by Project Co and/or the Trust.  This seems … to render the question of approval otiose”.

LDC (Portfolio One) Ltd v George Downing Construction Ltd & European Sheeting Ltd

In December 2022, the owner of student accommodation blocks in Manchester secured judgment in excess of £21 million for remedial works and lost rental income, against a specialist sub-contractor responsible for inadequate fire stopping/barriers, and composite cladding defects which led to substantial water ingress.  The claimant and first defendant agreed to settle the claims between them for c. £17 million shortly before trial; the second defendant was insolvent and unrepresented at the hearing, which proceeded in any event as the liquidator could not consent to judgment being entered.

Performance Standards

The defendant contractors were in each case appointed pursuant to JCT Design and Build Contracts, with terms including an unqualified design and specification duty, obligation to comply with statutory requirements, and duty to exercise reasonable skill and care.

The judgments include discussion on performance standards and reaffirm the MT Hojgaard [2017] UKSC 59 principle, that - if there are two clauses imposing different or inconsistent design requirements, the courts are likely to interpret the less demanding clause as a minimum obligation, since treating it as qualifying the other clause gives a meaning which effectively renders the more demanding provision redundant.  

The St James’s Oncology and LDC (Portfolio One) cases illustrate how bespoke amendments to standard form contracts may be used to improve prospects for recovery down the contractual chain, through “back to back” requirements for sub-contractors to indemnify the employer against liability arising under the main contract as a result of sub-contract breaches, and acknowledging that associated losses are within the parties' contemplation.

Building Regulations

The analysis of statutory requirements is particularly illuminating, in view of ubiquitous disputes over interpretation of relevant provisions now acknowledged by the government to have been “faulty and ambiguous”.

In Martlet v Mulalley, the judge concluded that Approved Document B (“ADB”), Fire Safety, 2000 edition (with 2002 amendments) does not mean that whatever was not expressly prohibited was permitted and acceptable; and ADB, 2006 edition, marked a significant change in guidance from the earlier regime, with only materials of limited combustibility to be used as external wall insulation in buildings over 18 metres.

Further, the Building Regulations 2000, Schedule 1, B(4)1 requirement for external walls to “adequately” resist the spread of fire, having regard to a building’s height, use and position, turned on whether the contractor had followed guidance in BRE 135 (2003), which recommended that combustible cladding should not be used on high rise residential blocks unless it met the Annex A performance standard in accordance with the test method set by British Standard 8414-1.  It was not sufficient to “blindly” rely on a British Board of Agrement (BBA) certificate for the cladding system.

Negligence

The selection and use of a cladding system with combustible EPS insulation in Martlet v Mulalley was in breach of the contractor’s obligation to exercise the degree of skill and care in its design of the work as would an architect or other professional designer.

In reaching this decision, the judge rejected defence arguments to the effect that they cannot have been negligent because everyone else was making the same mistakes.  On a proper application of the Bolam principle, there must be “evidence of a responsible body of opinion that has identified and considered the relevant risks or events and which can demonstrate a logical and rational basis for the course of conduct or advice that is under scrutiny”.  A defendant is not exonerated simply by proving that others were equally negligent (199 Knightsbridge Development Ltd v WSP UK Ltd [2014]).

Negligent design in relation to cladding works means that professional indemnity policies are likely to be triggered, and exclusions for contractual liabilities won’t usually apply.

Failure to comply with building regulations may be strong evidence of breach of a designer’s duty to exercise reasonable skill and care, in the absence of an express clause requiring adherence to statutory requirements, as discussed in LDC (Portfolio One).

Causation

Another defence commonly raised in cladding disputes is that enhanced fire safety standards implemented after completion of the contract works, and/or the changed regulatory perspective post-Grenfell, are the true cause of remedial action undertaken or proposed.  This was rejected in Martlet v Mulalley, with the judge suggesting that an “effective cause” test would be more appropriate to a “but for” standard in this case, to avoid the claimant being left without a remedy.

Had the building owner succeeded only on the installation breach, it could have recovered the cost of repairing defects but not those of replacing the cladding.  Both the installation and specification breach cases were upheld on the facts, so the owner was entitled to recover replacement costs.

Remedial Costs

In St James’s Oncology, the defendants’ argument that there was no intention to carry out remedial works was dismissed.  The court is not normally concerned with how the claimant will use any damages awarded, providing the loss can be established, although intention may be relevant to the reasonableness of reinstatement and thereby the extent of loss.  It was legitimate (and prudent) for the claimant to take account of commercial considerations and await conclusion of the proceedings before commencing planned remediation, given the defendants’ complete denial of liability until shortly before trial.

Remedial works to the Gosport towers were already complete when Martlet v Mulalley reached trial.  Costs incurred are the starting point for what is reasonable in such cases, especially if works are carried out based on expert advice.  The claimant has a duty to mitigate loss, “but the court will not be too critical of choices made as a matter of urgency or on incomplete information”.  It is not sufficient that defects could have been rectified more cheaply; the defendant must prove the remedial scheme was unreasonable.

Further, the costs of temporary measures such as waking watch patrols are likely to be recoverable.  The judge in Martlet v Mulalley dismissed the suggestion that this aspect of the claim was too remote, saying that any lack of awareness of the potential need for such interim protections in the context of combustible cladding was more reflective of a “culture of endemic complacency” than any reasoned assessment.

Where works of repair or reinstatement result in the claimant having a better or newer building than it would otherwise have had, a deduction for "betterment" will not usually be made if the claimant has no reasonable choice (Harbutt’s Plasticine v Wayne Tank [1970]).  This includes betterment resulting from compliance with legislation introduced since the original works were carried out, imposing additional or enhanced standards.

Looking Ahead

The emerging direction of travel underlines the difficulty for designers (and insurers) in defending these types of claims.

The Building Safety Act 2022 provides further impetus on cladding disputes, introducing new causes of action for defective works and construction products, subject to a maximum 30 years’ retrospective limitation period.  The Grenfell Inquiry phase 2 report is due for publication later this year, with Sir Martin Moore Bick’s findings expected to significantly impact upon the liability landscape, and potential manufacturer claims in particular.

Owners will look to progress claims swiftly in light of insolvency risks, with expert technical and quantum evidence crucial in justifying schemes of remedial work.  Construction professionals with cladding exposures will be keen to extricate themselves through commercial settlements, whilst pursuing possible recoveries.  Moving forward, contractors should endeavour to agree supply chains on back to back terms with their main contract, to limit exposures and improve prospects in the event of breach.

The courts’ focus on ensuring that buildings are made safe and compliant with current statutory requirements is closely aligned with public policy.  Further developments in this area, including jurisprudence around Building Liability Orders and s.38 of the Building Act 1984, for example, are eagerly anticipated.

Authors:

Amy Lacey is a Partner at Fenchurch Law

Grace Williams is an Associate at Fenchurch Law


Court hands down judgment in much anticipated Covid-19 BI cases: the takeaways for policyholders

Fenchurch Law represents Stonegate Pub Company Limited in its claim for Covid-19 business interruption losses against its three insurers: Ms Amlin; Liberty Mutual; and Zurich.

760 of Stonegate’s premises were insured under a Marsh Resilience wording, which was a wording considered by the Divisional Court and Supreme Court as part of the FCA Test Case. The Test Case confirmed that the policy responded to business interruption losses. However, a number of secondary issues remained in dispute despite the Courts having confirmed coverage.

The key issues for consideration were as follows:

  1. Trigger;
  2. Aggregation;
  3. Causation;
  4. Additional Increased Costs of Working (“AICW”); and
  5. Government Support.

In its judgment, notably, the Court rejected the Insurers’ primary argument that all cases aggregate to the emergence of the virus or pandemic, and agreed with Stonegate’s position that losses are recoverable after the end of the policy period. The Court found in favour of Insurers on other issues, and in particular with regard to furlough.

Below we consider the Court’s judgment in relation to each of the issues, as well as the related judgments in the cases of Greggs v Zurich [2022] EWHC 2545 (Comm) and Various Eateries v Allianz [2022] EWHC 2549 (Comm), and what they mean for policyholders.

Trigger

The Court was asked to consider the trigger (a colloquial shorthand for the matter or matters which gave rise to a right to claim under a policy) under the Disease, Enforced Closure and Prevention of Access perils present in the Marsh Resilience wording. The Court made the following findings:

  • The Disease peril is triggered whenever there were cases of Covid-19 which were either discovered at an insured location, or within the relevant vicinity, and each example is separate Covered Event;
  • The Enforced Closure peril triggered whenever all or part of an insured location was closed under a relevant compulsion or instruction. The policy is “triggered” in respect of each such closure, and the number of locations closed is the number of triggers. A location opening and then closing again at a different time would be considered a separate trigger;
  • The review, reiteration, continuation or renewal of regulations which were materially of the same effect does not constitute a separate closure or separate ‘trigger’;
  • The Prevention of Access peril trigger was the number of such actions or advices which prevented or hindered the use of or access to the insured location;
  • Steps or advice which merely repeated or renewed an existing prevention or hindrance of access forms part of one set of ‘actions or advice’, and therefore is only one ‘trigger’ or Covered Event;

Policyholders with different aggregation wording, or with no aggregation wording, could find the Court’s analysis on trigger particularly useful.

Aggregation

With regard to aggregation, ever the tricky area for policyholders and insurers alike, the Court considered the extent to which Stonegate’s claimed losses arose from, were attributable to, or were in connection with one more single occurrence for the purposes of aggregation as one or more Single Business Interruption Loss.

In determining the number and nature of occurrences, the Court had regard to ‘the degree of unity in relation to cause, locality, time, and, if initiated by human action, the circumstances and purposes of the persons responsible’. The Court also considered the concept of remoteness between the aggregating event and the loss, which acts as a counterbalance to the more aggressive aggregation clauses and issues that arise from causation.

Insurers maintained a number of alternative cases in relation to aggregation in an attempt to limit Stonegate’s losses to a single sub limit of liability to which all losses could be aggregated.

The Judge disagreed with a number of the Insurers’ proposed occurrences for the purposes of the aggregating wording, including tracing Covid-19 back to its evolutionary roots, the original zoonotic transmission of Covid-19 in Wuhan, and the virus’ entry into the UK. The Court rejected these arguments on the basis that these proposals were either geographically, temporally or causally too remote (or a combination of).

Instead, the Court held that there had been at least two occurrences that satisfied the relevant aggregating test and fell within Stonegate’s policy period (which ended on 30 April 2020), and acknowledged a possible third occurrence, being:

i) The decision taken at the COBR 16 March meeting to advise people to stop non-essential contact with other and to not visit crowed areas such as pubs, restaurant and clubs (a finding that went against the previously established precedent that a decision did not constitute an occurrence);

ii) The instruction given on 20 March that all pubs, bars and restaurants were to close; and

iii) The announcement of the national lockdown on 23 March 2020.

The Court considered that at this point in time the decisions taken by the devolved administrations were taken jointly, and therefore there was only one occurrence across the UK. However, the Court accepted that if it was wrong on this point, there would be an occurrence in the form of the decisions of each home nation.

It is notable, however, that there was no finding in relation to losses in the pre-aggregated period (16 March 2020), therefore, the occurrences thereafter did not aggregate any of the losses incurred before the COBR meeting on 16 March 2020.

The judgment does not consider other occurrences from 30 April 2020, as this is the date on which Stonegate’s policy expired. However, in Greggs v Zurich, the Court provided some further clarity for policyholders, and held that there was a separate occurrence for each announcement or measure relevant to Greggs’ business, with the exception of those that simply continued, made trivial changes to, or reduced existing restrictions.

In Greggs, the Court considered decisions taken from May 2020 by the home nations as being separate and therefore not single occurrences in the meaning the policy wording. The result is that business with locations in each administration will benefit from cover for a separate occurrence (and therefore a separate sub limit if applicable).

Policyholders with longer policy periods should be aware of other examples of an “occurrence” within the meaning of the Marsh Resilience aggregating wording, which may include:

i) In England, the bringing into force of the three-tiered system on 14 October 2020;

ii) The announcement and implementation of the second national lockdown,

iii) The announcement and implementation from 20 December 2020 of the Tier regulations;

iv) Restrictions imposed on limited areas of the country, for example, the local lockdown in Leicester on 04 July 2020.

Causation

Stonegate, as with most hospitality and leisure businesses, continued to feel the effects of Covid-19 long after the expiration of its policy period. The Court found that losses suffered after the expiry of the policy period were attributable to Covered Events, and rejected the Insurers’ argument that any losses suffered after the expiry of the policy period could not have been caused by a Covered Event.

Stonegate’s losses, from 1 May 2020 until 4 July 2020 (in England), 6 July 2020 (in Scotland) and 13 July 2020 (in Wales) were all proximately caused by Covered Events that occurred between 17 February and 30 April 2020.

Losses beyond those dates were considered to be in response to the subsequent developments of Covid-19, and predominantly caused by more recent cases.

The Court did accept that there were several individual categories of causal linkage that could continue after the dates outlined above, such as continued losses caused by deaths or long covid, and loss of momentum in relaunching premises prior to the expiry of the policy period.

Within those categories was the cancellation of events which had been organised to occur after the dates outlined above, by reason of uncertainty as to whether they would be able to go ahead. This category is undoubtably important to the hospitality industry, and the same logic may equally apply across other industries.

The Court gave further consideration to the issues of causation in Various Eateries v Allianz. The Court held that in Various Eateries’ circumstances (where this particular policy expired on 28 September 2020), cases of Covid-19 occurring in the Vicinity during the Period of Insurance were potential proximate causes of government action for a time after 28 September 2020 and in particular, that they were at least equal proximate causes of the tier system announced by the government on 14 October 2020 (but not the movement of some areas within the tier system to tier 2 on 29 October 2020).

The causation findings are very fact sensitive and will be dependent on the length of the policy, the length of the indemnity period and the significance to that policyholder’s business of the different announcements, measures and regulations.

AICW

The Court confirmed that AICW applied per Single Business Interruption Loss (i.e. per occurrence) and in addition to the notifiable disease sub-limit, but it did not apply to economic increased costs of working. The wording of the policy, correctly construed, meant that the AICW limit only applied to additional costs which were uneconomic (i.e. that which exceeds the amount of reduction in turnover avoided) but not to increased cost of working where the limit applicable to the ICW has been exhausted.

Government Support

The Court considered that payments received under the Coronavirus Job Retention Scheme (“CJRS”) should be taken into account for Insurers’ benefit when calculating sums recoverable by policyholders. The significance of this finding is subject to the wording of policy specific savings provisions. However, it is likely to be applicable to most policyholders (not just the Stonegate, Various Eateries and Greggs parties).

Payments made under the Business Rates Relied (“BRR”) would not be accounted for to insurer’s benefit if the business shows that normally business rates would have been paid out of turnover. Unlike the Court’s finding in relation to CJRS, the BRR is fact specific per policyholder.

Where next

A spokesperson for the Stonegate Group said:

The outcome of this case is far from conclusive. We are pleased that the Judge found in our favour on a number of key issues and note that he sided with our insurers on others. In this sense, the outcome is similar to the judgment of the Divisional Court in the Test Case brought by the FCA last year.

However, we believe that the Court’s interpretation on a number of issues which are generally applicable to policyholders is out of step with the approach taken by the Supreme Court in the Test Case and with the approach of Courts in other jurisdictions (such as on furlough). We intend to appeal those elements of the decision.

Whilst our recovery from the pandemic has been strong, we cannot ignore the significant disruption caused during the last two years and, along with most businesses in the UK, we are now grappling with inflationary challenges and a cost of living crisis for the UK consumer. In the circumstances, we, and other businesses, are entitled to look to our insurers to provide the cover promised under our policy

Copies of the judgments can be accessed here:

Stonegate - https://www.bailii.org/ew/cases/EWHC/Comm/2022/2548.html

Various Eateries - https://www.bailii.org/ew/cases/EWHC/Comm/2022/2549.html

Greggs - https://www.bailii.org/ew/cases/EWHC/Comm/2022/2545.html

 

Authors:

Anthony McGeough is an Associate at Fenchurch Law

Joanna Grant is a Partner at Fenchurch Law


Covid-19 BI Update: Access Granted to Corbin & King and Deduction of Furlough from Claims

“… the decision of the Supreme Court has moved the goalposts and the argument which has emerged is materially different.”

Mrs Justice Cockerill, Corbin & King v Axa [2022] EWHC 409 (Comm)

Two further policyholder-friendly judgments last week continued the trend of extending the scope of coverage available for Covid-19 BI losses under non-damage extensions. This time the focus falls on (i) prevention of access wordings; (ii) aggregation of losses at multiple premises; and (iii) deduction of furlough and other government support payments.

1. Prevention of Access – Access Granted!

In our September 2021 Update ‘‘Denial of Access – Access Granted", we set out Lord Mance’s reasoning in the China Taiping Arbitration, noting that it set out a clear pathway to coverage for policyholders with Prevention of Access and similar wordings, whose claims had been declined following the Divisional Court judgment in the FCA test case.

In a judgment handed down on Friday in Corbin & King v Axa, Mrs Justice Cockerill endorsed that approach and signalled a wholesale reversal of the coverage position under such wordings.

Recap

The FCA test case examined coverage under a number of non-damage Prevention of Access or Denial of Access clauses. At first instance, the Divisional Court found that the majority of such clauses provided a “narrow, localised form of cover” which did not respond to the broader circumstances of the pandemic. The basis for this conclusion was encapsulated at paragraph 467 of the Divisional Court judgment (repeated in similar terms elsewhere in relation to different wordings):

“There could only be cover under this wording if the insured could also demonstrate that it was an emergency by reason of COVID-19 in the vicinity, in that sense of the neighbourhood, of the insured premises, as opposed to the country as a whole, which led to the actions or advice of the government. […] it is highly unlikely that that could be demonstrated in any particular case[3].”

Many policyholders were disappointed at the FCA’s decision not to appeal that aspect of the Divisional Court judgment, and have subsequently argued that the Supreme Court’s ultimate conclusions on causation rendered the Divisional Court’s ruling an unsound authority for declining coverage under such clauses.

The China Taiping Arbitration

The point was subsequently argued on behalf of policyholders in the China Taiping Arbitration, decided by Lord Mance in a published award. Although the China Taiping policyholders’ claim ultimately fell down on the issue of whether the UK government was a ‘competent local authority’ within the meaning of the clause, on the key issue of whether the Covid-19 pandemic was capable of triggering coverage under a clause requiring, “an emergency likely to endanger life or property in the vicinity of the Premises” Lord Mance agreed with the policyholders that the position was indeed altered by the Supreme Court judgment in the test case.

In Lord Mance’s words:

“I therefore doubt whether the Divisional Court could or would have approached the matter as it did in paragraphs 466 and 467 had it had the benefit of the Supreme Court’s analysis.”

The door was therefore left wide open for the point to be fully argued before the Courts, which it duly was by Corbin & King in their case against Axa.

Corbin & King v Axa

In Corbin & King, the policyholders sought coverage for their BI losses flowing from closure and other restrictions places on eight insured restaurants, under a Non-Damage Denial of Access (NDDOA) clause, which responded to:

“the actions taken by police or any other statutory body in response to a danger or disturbance at your premises or within a 1 mile radius of your premises.”

Insurers denied coverage in reliance on the Divisional Court, in much the same terms as China Taiping.

Coverage

On behalf of Corbin & King  Jeffrery Gruder QC argued, relying on Lord Mance’s reasoning in China Taiping,  that government action to close down the insured restaurants had been taken in response to the nationwide pandemic, that included cases of Covid-19 within a 1 mile radius of the insured premises, which amounted to a danger. On the Supreme Court’s concurrent causation analysis, the action had been taken in response to a danger or disturbance within 1 mile of the premises, which therefore was a proximate cause of loss, triggering coverage under the NDDA clause.

Axa for its part contended that the Supreme Court’s findings on causation could not be transposed from disease clauses to prevention of access clauses, which were qualitatively different, but that in any case in the present case the insured peril had simply not been triggered. There had been no “danger or disturbance at the insured premises or within a 1-mile radius of the insured premises”, and the question of causation did not therefore arise.

Mrs Justice Cockerill first concluded that she was not bound by the ruling of the Divisional Court, not only because the Axa clause was sufficiently different from the clauses considered in the test case, but also because the Supreme Court decision in the test case had “moved the goalposts”, and that consequently the legal argument had “developed somewhat … in the way that legal argument inevitably develops, like water, to find its way round an obstacle.”

Approaching the matter from first principles, but drawing heavily on the Supreme Court’s ruling on concurrent causation, and Lord Mance’s persuasive discussion of the issue, Cockerill J therefore found that:

  • Covid-19 was capable of being a danger within one mile of the insured premises;
  • which, coupled with other uninsured but not excluded dangers outside;
  • led to the regulations which caused the closure of the businesses and caused the business interruption loss.

There was therefore cover for Corbin & King’s losses under the Axa NDDOA clause.

2. Prevention of Access - Aggregation

A secondary issue was whether the limit of £250,000 available under the NDDOA clause applied as an aggregate limit to Corbin & King’s losses, or to each of the eight insured premises. Axa accepted that a fresh limit applied for each new set of government restrictions, but maintained that in each case the limit applied to Corbin & King’s business as a whole, and not to each restaurant individually.

On that issue the Court also found in the Claimants’ favour, for two reasons.

First, as Corbin & King pointed out, their policy was a composite one under which the insurer had agreed to indemnify a number of different insured entities, each holding one or more insured premises. The Court found that the insureds’ interest was not joint, and that each had their own claim under the policy.

Moving on to construction, Cockerill J noted that the policy referred to cover in respect of interruption and interference with the business where access to the Premises was restricted, and that each of the Premises was in a different location. The closure of two restaurants “must be seen on any analysis as two separate incidents”, and that was said to be regardless of whether there was one common danger causing the closure, or two separate dangers. The word “premises” pointed to each restaurant/café, and that pointed to separate limits.  Cockerill J found that these were powerful points that unequivocally supported the Claimant’s position, and therefore had no difficulty concluding, apparently regardless of the ‘composite policy’ issue, that the Policy provided a separate limit of £250,000 for each insured restaurant.

The ruling marks the first aggregation decision in the Covid-19 BI context, and may serve to dramatically increase insurers’ liability in cases where policyholders have insured multiple locations under a single policy.

3. Furlough and Government Support

A near-universal point of contention in the adjustment of Covid-19 BI claims (where coverage is established), has been the treatment of certain types of government financial support received by policyholders. While insurers have by and large agreed that government grants are to be ignored for the purposes of a BI indemnity, they have generally maintained that any support received in the form of Coronavirus Job Retention Scheme payments (“Furlough”), and Business Rates Relief, should be either be accounted for as turnover or as a saving, thus reducing the value of the covered claim under the Policy.

For their part, many policyholders have maintained that (i) the terms of the policies do not generally support such an approach; (ii) as a matter of common law, such payments do not go to reduce the policyholders’ covered loss, and (iii) as a matter of public policy, government financial support provided to the hospitality industry and other hard-hit sectors was not intended to inure to the benefit of insurers.

Insurers’ approach has had the effect of drastically reducing, or in some cases effectively wiping out, the amount paid by the insurer to policyholders for their claims. The underlying question therefore remains: who should stand first in line to benefit from the government’s financial support measures – the hospitality industry which is still struggling to recover 2 years later, or insurers, who were largely cushioned from the effects of the pandemic, and who have in many cases reported record profits in 2021?

The issue remains untested in the English courts, although a distinguished panel led by Lord Mance in the Hiscox Action Group Arbitration was reported in July 2021 to have found in favour of the policyholders on the issue.

More recently, in the second Australian test case[1], the Federal Court of Australia found at first instance that JobKeeper payments (the Australian equivalent of furlough) were properly deductible from Covid-19 BI claim calculations as a saving. That decision was appealed to the Full Court of the Federal Court of Australia, which last week overturned the ruling and found that JobKeepers payments, and certain other forms of government support, were not to be treated as a saving because they were not made and received “in consequence of” the interruption or interference resulting from the insured peril, i.e. the policyholder would have received the payments regardless of whether there had been an outbreak of disease within the specified radius of the premises.[2]

Whilst the decision of the Australian Full Court is not binding on UK insurers, it provides further support for policyholders’ position in the UK, and will no doubt come under close scrutiny by the Commercial Court, when the issue falls for determination for the first time in the English courts in the forthcoming trial of Stonegate v MS Amlin in June 2022[3].

4. Comment

This week’s developments will come as welcome news to a great many policyholders who have either had their Covid-19 BI claims declined under Prevention/Denial of Access wordings, or who have had the value of their claims reduced for government support received. The Corbin & King decision will also serve as an important authority for those policyholders who are seeking full indemnity for losses suffered at multiple premises. Policyholders in any of these groups should now therefore review their position with their advisors, to consider whether any further action is now required.

Aaron Le Marquer is a Partner at Fenchurch Law

 

[1] Swiss Re International Se v LCA Marrickville Pty Limited (Second COVID‑19 insurance test cases) [2021] FCA 1206

[2] LCA Marrickville Pty Limited v Swiss Re International SE [2022] FCAFC

[3] https://www.judiciary.uk/you-and-the-judiciary/going-to-court/high-court/queens-bench-division/courts-of-the-queens-bench-division/commercial-court/test-and-grouped-cases-including-covid-19-bii-cases/

 


Fenchurch Law gavel

Guilty as charged? Berkshire Assets (West London) Ltd v AXA Insurance UK PLC

In one of the first cases to be decided under the Insurance Act 2015 (“the Act”), the High Court was asked to consider whether an insured breached its duty of fair presentation under the Act by failing to disclose criminal charges against one of its directors.

Background

In 2018, Berkshire Assets (West London) Limited (“Berkshire”), purchased a Construction All Risks and Business Interruption Policy (“the Policy”) underwritten by AXA Insurance UK Plc (“AXA”) for a property development project in Brentford.

The quote contained a number of provisions, including the following:

The proposer for insurance, its partners or directors or any other person who plays a significant role in managing or organising the business activities, have not, either personally or in any business capacity, been convicted of a criminal offence or charged (but not yet tried) with a criminal offence.”

The policy renewed in 2019. Unbeknown to the director who was tasked with handling its insurances, one of its other directors, Mr Sherwood (and various other companies and individuals), had criminal charges filed against him by the Malaysian public prosecutor in August 2019 in connection with a $4.3bn fraud.

In January 2020, an escape of water resulted in substantial damage to the development. Berkshire thereafter made a claim under the Policy.

After investigating the claim, AXA avoided the Policy on the basis that Berkshire failed to disclose the charges against Mr Sherwood at renewal, and, had it done so, said that cover would not have been provided.

Berkshire argued that Mr Sherwood was not personally involved in the planning, approval or execution of the transactions which gave rise to the charges. To the contrary, the charges related solely to his capacity as a director of an investment banking company.

Issues for the Court

There were two issues for the Court to consider:

  1. Were the charges against Mr Sherwood material, for the purposes of the duty of fair presentation?
  2. If they were, and had they been disclosed, would AXA have agreed to insure Berkshire?

Materiality

The Court considered the definition of a material circumstance under section 7(3) of the Act. This provides that a circumstance is material if it would influence the judgment of a prudent insurer in determining whether to take the risk, and if so, on what terms.

The Court agreed with AXA that the principles relevant to material circumstances were already well established, and there was no reason to suggest that the Act had changed those principles.

There was, however, a debate about whether the charges against Mr Sherwood amounted to a moral hazard which Berkshire was required to disclose.

The Court considered there to be no settled definition of ‘moral hazard’, as each case will necessarily depend on its own facts. It was therefore preferable, in this instance, to rely on the statutory definition of material circumstance when considering the facts of the case before it.

In considering materiality, the Court found that being charged with a criminal offence will often constitute a material circumstance (March Cabaret Club v. London Assurance [1975] 1 Lloyd’s Rep. 169). Also, the time such facts are to be considered is at the time of the renewal, and not with the benefit of hindsight (Brotherton v. Aseguradora Colseguros (No. 2) [2003] EWCA Civ 705, 1 Lloyd’s Rep. IR 746). Therefore, the fact that the charges were dismissed was ultimately irrelevant.

The fact that the charges did not relate to deceit or dishonesty was equally irrelevant, as AXA could not be expected to resolve the issue of whether or not they involved allegations of deceit or dishonesty at renewal. Facts raising doubt as to the risk were, without more, sufficient to be material, and the Court therefore found they should have been disclosed.

Inducement

It was common ground between the parties that AXA’s branch office had no authority to write the risk under an internal practice note that had been disclosed. The Court found that there was no reason to suppose that the regional or London offices would have considered the matter any differently if the charges against Mr Sherwood had been disclosed, nor was there a reason that the conclusions of the underwriting team would have been any different.

Comment

The case is a salutary reminder for policyholders and brokers that questions around criminal conduct and charges, whether proven or otherwise, are likely to be material. A thorough investigation into all directors’ backgrounds is advisable at each renewal, and when in doubt, it is better to err on the side of caution.

Authors:

Alex Rosenfield, Senior Associate

Anthony McGeough, Associate


Fenchurch Law gavel

Stonegate v MS Amlin & Ors

Commercial Court Claim no. CL-2021-000161

Background

Fenchurch Law is representing Stonegate Pub Company Limited in its claim for Covid-19 business interruption losses against three insurers: MS Amlin, Zurich, and Liberty Mutual.

Stonegate owns and operates over 4,500 public houses, bars, restaurants and other hospitality businesses in the UK and, like all hospitality businesses, suffered interruption and interference to its business as a result of the emergence of the Covid-19 pandemic, and the government’s actions in response.

The three insurers in the case provided coverage for 760 of Stonegate’s establishments under a policy issued using the Marsh Resilience wording, which was one of the representative sample of wordings considered by the Court in the FCA test case. The test case confirmed that the Resilience wording was capable of responding to business interruption losses arising from the Covid-19 pandemic under three insuring clauses, and insurers have not challenged those findings. Coverage is therefore not in dispute.

The Issues in the Case

Stonegate’s case focuses on the limits of liability available to meet Stonegate’s losses, which itself turns on four issues of principle:

(i) Aggregation

The case will determine how Stonegate’s losses suffered at different locations, at different times, and in different ways are to be aggregated for the purposes of the relevant (sub)-limits of liability. Insurers contend that Stonegate’s losses are to be aggregated as one ‘Single Business Interruption Loss’, and that its claim for Business Interruption Loss is therefore subject to a single (sub)-limit of liability of £2.5m. Stonegate claims that it is entitled to claim multiple (sub)-limits of liability. The outcome of the issue will depend in part on the court’s determination of the meaning of the term “occurrence” in the context of Stonegate’s policy.

(ii) Causation of Post Policy Period Losses

The policy provides a Maximum Indemnity Period of 36 months. Stonegate, like all hospitality operators, continued to suffer loss after the expiry of its policy period. The case will determine the applicable indemnity period(s) to Stonegate’s claim, and specifically how long the indemnity period extends after the expiry of the policy period.

(iii) Additional Increased Costs of Working

In addition to cover for Business Interruption Loss, the policy provides cover for Additional Increased Costs of Working. The case will determine the limit of liability under this cover, and the nature of the costs that may be claimed.

(iv) Government Support

Insurers contend that as a matter of law and/or the proper construction and/or application of the policy, governmental support (including Coronavirus Job Retentions Scheme payments or “furlough” payments, and Business Rates Relief) is to be taken into account for the insurers’ benefit when calculating any Business Interruption Loss and/or other sums recoverable under the policy. Stonegate denies that insurers are entitled to make any deduction from its claim in respect of these kinds of governmental support.

The respective positions of the parties are set out in detail in the statements of case, which are documents of public record, and may be downloaded below:

Amended Particulars of Claim

Defence

Reply

Updates

Because of the relevance of these issues to many other policyholders with unresolved Covid-19 business interruption claims, including those insured under the Marsh Resilience wording as well as those under other policy wordings, Stonegate recognises that the outcome of the case is of significant interest to many market stakeholders.  Fenchurch Law will therefore share regular updates on the progress of the case.

Current Procedural Status

The case is currently listed for a Case Management Conference on 29 October. At that hearing, the Court will hear the parties’ proposals for the management of the case, and may give directions as to timetable, procedure and any other preliminary matters.

A further update will be posted sharing any Order granted by the Court following the CMC.


Covid-19 BI Update: Denial of Access – Access Granted?

“I doubt whether the Divisional Court could or would have taken the approach it did, had it had the benefit of the Supreme Court’s reasoning on causation.”

Lord Mance

The latest Covid-19 BI decision to arrive following the conclusion of the test case provides fresh hope for policyholders with denial of access clauses whose claims currently remain declined.

It will be recalled that the Divisional Court in the test case found that such clauses provided a “narrow, localised form of cover” which did not respond to the broader circumstances of the pandemic. Many policyholders were disappointed at the FCA’s decision not to appeal these rulings, and have subsequently argued that the Supreme Court’s ultimate conclusions on causation rendered the Divisional Court’s ruling an unsound authority for declining coverage under such clauses.

In an arbitral Award issued on 10 September 2021 by Lord Mance[1], clear support is provided for exactly that proposition.

The China Taiping Proceedings

In arbitration proceedings commenced by Fenchurch Law on behalf of a group of 183 hospitality policyholders against China Taiping Insurance[2], coverage was considered under two limbs of a Denial of Access clause which responded to:

b – the closing down or sealing off of the Premises or property in the vicinity of the Premises in accordance with instructions issued by the Police or other competent local authority for reasons other than the conduct of the Insured or any director or partner of the Insured or the condition of the Premises or the carrying out of repair or maintenance work at the Premises;

c – the actions or advice of the Police or other competent local authority due to an emergency threatening life or property in the vicinity of the Premises;”

The Issues

There were three key disputed issues. First, whether the existence of Notifiable Disease cover elsewhere in the policy (which did not extend to Covid-19) negated the possibility of the Denial of Access wording responding to the pandemic. Secondly, whether the requirement for an “emergency in the vicinity of the premises” in limb (c) meant that the clause could only respond to narrow, localised events, rather than national ones, per the Divisional Court decision in the test case. Thirdly, whether the UK Government was a ‘competent local authority’ within the meaning of the clause.

On the first issue, Lord Mance found in favour of the policyholders. The existence of the express notifiable disease cover elsewhere in the policy did not limit the cover under the prevention of access extension.  It was common for the coverage provided by various insuring clauses and extensions to overlap, and if insurers intended to exclude diseases from the scope of the prevention of access clause, they should have used clear language to do so.

On the third issue, Lord Mance agreed with insurers that the UK Government was not a “competent local authority” within the meaning of the clause, meaning that there could be no coverage under limbs (b) or (c) of the Denial of Access extension for losses caused by closures and other restrictions imposed by the UK Government in response to the Covid-19 pandemic. This issue was ultimately therefore fatal to the policyholders’ claim, which failed at the last hurdle.

Issue 2 – Emergency threatening life or property in the vicinity of the premises

On Issue 2, however, Lord Mance agreed with the policyholders, and despite the fact that it did not alter the outcome in this particular case, his discussion and conclusions on the issue are of potentially much broader significance and merit close examination.

Lord Mance noted that Clause 1(c) was drafted in materially identical terms to two of the representative sample of policy wordings considered in the test case, namely RSA 2.1 and 2.2. The RSA clauses required “an emergency likely to endanger life or property in the vicinity of the Premises”.

In the test case, the Divisional Court concluded in relation to RSA 2.1 and 2.2, that

There could only be cover under this wording if the insured could also demonstrate that it was an emergency by reason of COVID-19 in the vicinity, in that sense of the neighbourhood, of the insured premises, as opposed to the country as a whole, which led to the actions or advice of the government. […] it is highly unlikely that that could be demonstrated in any particular case[3].”

Similar conclusions were reached in relation to the other denial of access wordings under consideration, and the findings were not appealed to the Supreme Court.  In the arbitration, insurers unsurprisingly therefore relied on the Divisional Court’s judgment to resist coverage under limb 1 (c) of the China Taiping clause.

Lord Mance began his analysis of the issue by noting that, as an arbitrator, he must regard the Divisional Court’s approach to the NDDA clauses as being, at the very least, highly persuasive, and that it may even, on the face of it, bind him.  However, that was subject to, first, the relevant point having been squarely argued and decided in the Divisional Court, and second the Supreme Court’s judgment.

As to the first point, Lord Mance noted that the Divisional Court appeared to have reached its conclusions on the basis that RSA 2.1 and 2.2 were analogous with MSA 1.  However, in Lord Mance’s view, the China Taiping and RSA wordings were clearly distinguishable from the MSA 1 wording, in leaving open for consideration whether cover extends to an emergency outside the vicinity threatening life or property within the vicinity, in contrast with the MSA 1 wording that required that the emergency be within the vicinity of the premises.  It was unclear how far RSA had argued the point, but a requirement that the emergency be in the vicinity of the premises was central to the Divisional Court’s reasoning in relation to RSA 2.1 and 2.2.

In relation to the Supreme Court judgment, Lord Mance’s words speak for themselves:

“…although there was no appeal in respect of RSA2.1 and 2.2, I find the Supreme Court’s analysis of the operation of other wordings, and particularly its analysis of the correct approach to causation, hard to reconcile with the analysis of RSA 2.1 and 2.2 adopted by the Divisional Court in paragraphs 466 and 467.[…] Paragraphs 466 and 467 of the Divisional Court’s judgment indicate that it was the Court’s view of the causation required that ultimately dictated the likelihood of recovery under the relevant wordings.  The Supreme Court held that the Divisional Court had erred in significant respects in its understanding of the operation of causation under other policy wordings before it.  As I read its judgment, the Supreme Court also thought that its understanding would, at least prima facie, carry through generally into other wordings.”

“… the Supreme Court was, contrary to the Insurer’s submission, prepared to state quite generally that its general approach to causation was applicable across the whole range of wordings”

“That is particularly so, if the emergency may be outside the vicinity, so long as it threatens life or property within the vicinity.  But it is also so if both the emergency and the threat must be in the vicinity.  Once it is accepted that the emergency may at the same time be elsewhere and threaten life or property elsewhere, the Supreme Court’s analysis of the relevant elements of cover and its conclusion that a “but for” test of causation was inappropriate would seem readily transposable to a NDDA clause like Extension 1(c)”

“I therefore doubt whether the Divisional Court could or would have approached the matter as it did in paragraphs 466 and 467 had it had the benefit of the Supreme Court’s analysis.”

“The absence in the Arch wording of the words “in the vicinity” in relation to the emergency appears an inadequate basis on which to distinguish the Supreme Court’s approach in relation to that Arch wording from the present.”

Lord Mance apparently therefore concluded that he was not bound by the Divisional Court’s findings as far as relevant to Issue 2, and despite the negative outcome in the present case, set out a powerful and clear basis on which a case for coverage under the RSA 2.1 and 2.2 wordings (and others on similar terms, including the other denial of access wordings considered in the test case) might be made in reliance on the Supreme Court judgment.

Comment

Lord Mance’s comments in the China Taiping Award are far from the end of the story.  The Award is not binding on any third party, and despite his detailed and helpful analysis, Lord Mance found it unnecessary to issue any final ruling or declaration on the issue, due to his conclusions on the meaning of ‘competent local authority’ which were conclusive to the outcome of the proceedings.  Noting that the issue was complex, and because the Award was to be published and the issue may arise in other contexts, Lord Mance concluded that he should say “nothing more definite” about it.

But as an ex-Deputy President of the Supreme Court and the author of many seminal decisions on English insurance law, his clearly-expressed views on the matter will doubtless be influential in future judicial consideration of the issue, and will need to be studied closely by insurers and policyholders alike in considering the position under Denial of Access and other clauses where coverage is still in dispute.

A copy of the award can be accessed here.

[1] The arbitration proceedings were brought with the agreement of the insurer, who agreed to cover the costs of the proceedings, and not to seek its own costs from the policyholders regardless of the outcome.  Confidentiality in the arbitral award was also waived, meaning that it can be made public.

[3] Divisional Court para.467


Webinar - Covid-19 BI Litigation: the Second Wave

 

Agenda

It is now over five months since the Supreme Court handed down its largely policyholder-friendly judgment in the FCA Test Case, but for a majority of policyholders, the end is not yet in sight.

Our webinar examines the second wave of Covid-19 BI litigation now emerging in relation to a host of issues left undetermined by the Test Case, including:

– Disease ‘at the premises’ clauses;
– Prevention of Access clauses;
– Aggregation;
– Furlough and other government support;
– Loss of Rent

Aaron Le Marquer is a partner at Fenchurch Law